Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 21 | 21 | 21 | 0 |
1W356 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश सं0 5988/।।। (2)/15-11 (मु0मं0घो0)/2015 दि0 18.08.2015
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
0.92
Resanction Cost :
0.92
Tentative Cost :
0.92
Exp. Upto Last Fy : 0.24
For CFY 2024-2025
Remaining : 0.68
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.24
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 10 months ago
18 Aug 2015
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्थल चयन प्रस्ताव अधीक्षण अभियन्ता, प्रथम वृत्त, लो0नि0वि0, अल्मोड़ा के पत्रांक 3080/290सी0 -01/18 दिनाक 17.07.2018 द्वारा अनुमोदित। पुल के विस्तृत आगणन गठन की कार्यवाही गतिमान है। -- as on 02-Aug-2021
Physical Peramenters