Work Profile Report [1W381]
Fin Plan
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शासनादेश सं0 2103/।।। (2)/16- 52 (एम0एल0ए0)/2015 दि0 11.07.2016
TS Amount (lakhs) : 493.42 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
493.42
Resanction Cost :
493.42
Tentative Cost :
493.42
Exp. Upto Last Fy :
113.80
For CFY 2024-2025
Remaining :
379.62
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
113.80
Construction Started
Sanction on : 8 years 4 months ago
11 Jul 2016
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
40 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.87 कि0मी0 पहाड़ कटान पूर्ण। सेतु निर्माण कार्य विश्व बैैंक यू0डी0आ0पी0 खण्ड बागेश्वर द्वारा किया जाना है। -- as on 10-Nov-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand