Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.76 | 0.76 | 0.76 | 0 |
1W429 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शाशनादेश सं0 80(ए)/।।।(2)/18-52 एम0एल0ए0/2017 दिनांक 16.01.2018
TS Amount (lakhs) : 32.79 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
32.78
Resanction Cost :
32.79
Tentative Cost :
32.79
Exp. Upto Last Fy : 27.20
For CFY 2024-2025
Remaining : 5.59
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 27.20
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 6 months ago
16 Jan 2018
Tentative Completion date:
2 years 9 months ago
30 Sep 2021
Actual Completion Date:
2 years 9 months ago
30 Sep 2021
Remark
Bottelneck: no issue
कार्य्र पूर्ण माह 09/2021 दायित्व शेष। -- as on 11-May-2023
Physical Peramenters