Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 4 | 0 |
1W458 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 563/।।।(2)/19- 51(एम0एल0ए0)/2017 टी0सी0 दिनंाक 04.02.2019
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
16.96
Resanction Cost :
16.96
Tentative Cost :
16.96
Exp. Upto Last Fy : 0.34
For CFY 2024-2025
Remaining : 16.62
Demand : 0.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.34
Alignment Approved
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 4 months ago
18 Feb 2019
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 02: Division
Bottelneck: no issue
वन भूमि प्रस्ताव आंन लाईन। वर्तमान में प्रस्ताव नोडल अधिकारी स्तर पर है। -- as on 30-Jun-2023
Physical Peramenters