Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 |
1W462 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश संख्या 1316/।।।(2)/19-53 (एम0एल0ए0)/2017टी0सी0 दिनांक 07 मार्च, 2019
TS Amount (lakhs) : 163.2 Lacs
Financial Detail
Sanction Cost : 163.20 Lacs
Resanction Cost : 163.20 Lacs
Exp. Upto Last Fy : 122.90 Lacs
For CFY 2024-2025
Remaining : 40.30 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 122.90 Lacs
In Maintenance After Completion
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 years 2 months ago
07 Mar 2019
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
1 year 1 month ago
19 Apr 2023
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
कार्य पूर्ण माह 03/2022 -- as on 02-May-2023
Physical Peramenters