Work Profile Report [1W570]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO letter no5304/III(2)/21-52(MLA)/2015 दिनांक 01-11-2021
TS Amount (lakhs) : 66.31 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
66.31
Resanction Cost :
66.31
Tentative Cost :
66.31
Exp. Upto Last Fy :
0.11
For CFY 2024-2025
Remaining :
66.20
Demand :
45.00
Allotment :
12.72
Exp in CFY :
12.72
Total Up to Date Exp :
12.83
Construction Started
Sanction on : 3 years 1 month ago
01 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
10 %
Tentative Completion date on : 3 months 5 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work is in Progress. -- as on 17-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: