Work Profile Report [1W579]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : GO letter no 1352/III(2)/21-52(MLA)/2017 TC दिनांक 20-05-2021
TS Amount (lakhs) : 50.01 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.01
Resanction Cost :
50.01
Tentative Cost :
50.01
Exp. Upto Last Fy :
51.00
For CFY 2024-2025
Remaining :
-0.99
Demand :
0.00
Allotment :
-0.99
Exp in CFY :
1.38
Total Up to Date Exp :
52.38
Work completed
Sanction on : 3 years 7 months ago
20 May 2021
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 2 months 2 weeks from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Work Completed. -- as on 21-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: