Work Profile Report [1W65]

गोलूछीना गल्ली बस्यूरा गोबिन्दपुर मो0मा0 (10मी0 आर0सी0सी0 सेतु)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 2454/।।।-02/05-07 प्रा0आ0/05 टी0सी0 दि0 28.़10.05 ( मु0म0घो0)

TS Amount (lakhs) : 106 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

106.00

Resanction Cost :

106.00

Tentative Cost :

105.00

Saving

1.00

Exp. Upto Last Fy :

100.93

For CFY 2024-2025

Remaining :

5.07

Demand :

2.50

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

100.93

Construction Started

Sanction on : 19 years 2 weeks ago

28 Oct 2005

Physical Progress:

At start of FY 2024-2025 :

76 %

Up to Date :

76 %

Tentative Completion date on : 4 months 2 weeks from now

30 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
7
6.1
6.1
-
Bridge
1 (10m)
1 (10m)
1 (10m)
-

Remark

view all

कार्य पूर्ण दायित्व अवशेष। -- as on 03-Aug-2024

Rating : 99

Forest Case Pending At : 01: Withdraw

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand