Work Profile Report [1W70]

कठपुड़िया बंगसर मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शा0सं0 764/।।।(2)/08-65 (प्रा0आ0) / 07 दिनंाक 24.03.2008

TS Amount (lakhs) : 105 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

105.00

Resanction Cost :

105.00

Tentative Cost :

105.00

Exp. Upto Last Fy :

0.74

For CFY 2024-2025

Remaining :

104.26

Demand :

25.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.74

Construction Started

Sanction on : 16 years 4 months ago

24 Mar 2008

Physical Progress:

At start of FY 2024-2025 :

25 %

Up to Date :

25 %

Tentative Completion date on : 7 months 2 weeks from now

31 Mar 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
1.000
2
0.500
0.000

Remark

view all

1 कि0मी0 पहाड़ कटान एवं पार्ट-।। का कार्य पूर्ण। अवशेष कार्य की विधिवत् स्वीकृति प्राप्त । अवशेष कार्य किया जाना है। -- as on 03-Aug-2024

Rating : 27

Forest Case Pending At : 18: Final Approval

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: