Work Profile Report [1W759]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E - File No. 49618
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
304.22
Resanction Cost :
304.22
Tentative Cost :
270.54
Saving
33.68
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
304.22
Demand :
180.00
Allotment :
70.28
Exp in CFY :
70.28
Total Up to Date Exp :
70.28
Construction Started
Sanction on : 1 year 2 months ago
18 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
5 %
Up to Date :
40 %
Tentative Completion date on : 5 months 2 days from now
24 May 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 33.68 has been recorded as expected cost of work reduced from 304.22 to 270.54 . -- as on 19-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: