Work Profile Report [1W767]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E - File No. 49007/2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
188.09
Resanction Cost :
188.09
Tentative Cost :
180.00
Saving
8.09
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
188.09
Demand :
90.00
Allotment :
31.15
Exp in CFY :
31.15
Total Up to Date Exp :
31.15
Construction Started
Sanction on : 10 months 2 weeks ago
29 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
40 %
Tentative Completion date on : 7 months 1 week from now
27 Jul 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 8.09 has been recorded as expected cost of work reduced from 188.09 to 180.00 . -- as on 07-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: