Work Profile Report [20W187]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 1110/।।। (2) /14-52 (प्रा0आ0) / 2013 दि0 20 फरवरी 2014
TS Amount (lakhs) : 10 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
58.50
Resanction Cost :
58.50
Tentative Cost :
1.25
Saving
57.25
Exp. Upto Last Fy :
0.83
For CFY 2025-2026
Remaining :
57.67
Demand :
0.40
Allotment :
0.40
Exp in CFY :
0.40
Total Up to Date Exp :
1.22
Work deferred
Sanction on : 11 years 9 months ago
20 Feb 2014
Physical Progress:
At start of FY 2025-2026 :
75 %
Up to Date :
75 %
Tentative Completion date on : 1 year 7 months from now
01 Aug 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 57.25 has been recorded as expected cost of work reduced from 58.5 to 1.25 . -- as on 12-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: