Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
20W293 :
Administrative Approval Detail : शा0 3387 /।।। (2) /17-45 (एम0एल0ए0) / 2017 दि0 29-11-2017
TS Amount (lakhs) : 4.34 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
63.90
Resanction Cost :
63.90
Tentative Cost :
63.90
Exp. Upto Last Fy : 16.16
For CFY 2024-2025
Remaining : 47.74
Demand : 0.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 16.16
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 7 months ago
29 Nov 2017
Tentative Completion date:
1 year 11 months from now
12 Jul 2026
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
मुआवजा वितरित किया जा चुका है। दि0 11.01.2024 को विधिवत स्वीकृति प्राप्त । -- as on 26-Apr-2024
Physical Peramenters