Work Profile Report [20W34]

पोखरी चण्डिकाघाट मोटर मार्ग का विस्तार एवं सेतु (80मी. स्पान)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Nabard
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0 सं0 2503/111 (2)/06 -37 (प्रा0आ0) /06 दि0 20/9/06

TS Amount (lakhs) : 402.8 Lacs

Budget Financial Head : NABARD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

402.80

Resanction Cost :

402.80

Tentative Cost :

402.80

Exp. Upto Last Fy :

342.24

For CFY 2024-2025

Remaining :

60.56

Demand :

2.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

342.24

In Maintenance After Completion

Sanction on : 18 years 2 months ago

20 Sep 2006

Physical Progress:

At start of FY 2024-2025 :

60 %

Up to Date :

100 %

Tentative Completion date on : 2 years 3 weeks ago

31 Oct 2022

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
7.75
6.000
1.75
0.000
0.000
Bridge
1 (80m)
1 (80m)
0 (0.000m)
1 (80m)
0 (0.000m)
0 (0.000m)

Remark

view all

इस कार्य की स्वीकृति नावार्ड -27 में 09/2021 में 6 किमी0 लम्वाई हेतु प्राप्त हुई थी । नावार्ड के अन्तर्गत स्वीकृत 6 किमी0 में वर्ष 2022 में कार्य पूर्ण कर लिया गया है। 5 वर्षीय अनुरक्षण का कार्य प्रगति में है। -- as on 04-Jul-2024

Rating : 100

Forest Case Pending At : 14: AIP Conservator

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: