Work Profile Report [20W35]

चोड़मन्या कमतोली मोटर मार्ग का निर्माण
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

Administrative Approval Detail : शा0 सं0 2503/111 (2)/06 -37 (प्रा0आ0) /06 दि0 20/9/06

TS Amount (lakhs) : 178 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

178.00

Resanction Cost :

178.00

Tentative Cost :

178.00

Exp. Upto Last Fy :

134.52

For CFY 2024-2025

Remaining :

43.48

Demand :

25.00

Allotment :

25.00

Exp in CFY :

4.28

Total Up to Date Exp :

138.80

Construction Started

Sanction on : 17 years 10 months ago

20 Sep 2006

Physical Progress:

At start of FY 2024-2025 :

70 %

Up to Date :

70 %

Tentative Completion date on : 2 months 2 days from now

19 Oct 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
10
10
3.550
6.45
0.450
0.000

Remark

view all

निविदा कम दरों में प्राप्त हुई हैं जिस कारण वचत हो रही है तथा उक्त वचत को पुनरीक्षित आगणन में समायोजित कर लिया जायेगा।

इस मार्ग की मूल स्वीकृति 10 किमी0 है। विस्तृत सर्वेक्षण के पश्चात मार्ग की वास्तविक लम्बाई 7.800 किमी0 है।
वास्तविक लम्बाई के सापेक्ष 3.550 किमी0 में मार्ग निर्माण कार्य पूर्व में पूर्ण कर लिया गया था। इस वित्तीय वर्ष में 0.450 किमी0 मे पहाड़ कटान का कार्य पूर्ण कर पार्ट -।। का कर्य प्रगति में है।
अवशेष 3.8 किमी0 लम्बाई में निर्माण कार्य हेतु पुनरीक्षित डी0पी0आर0 बनाई जा रही है जिसे 05.08.2024 तक वृत्तीय कार्यालय को प्रेषित कर ली जायेगी।
-- as on 21-Jul-2024

Rating : 80

Forest Case Pending At : 13: AIP DFO

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: