Work Profile Report [20W394]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : मुख्य विकास अधिकारी पिथौरागढ़ का पत्राॅक 181 /वा0जि0यो0 /2021-22 दि0 25-05-2021
TS Amount (lakhs) : 40.38 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
28.42
Resanction Cost :
28.42
Tentative Cost :
28.42
Exp. Upto Last Fy :
6.67
For CFY 2025-2026
Remaining :
21.75
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
6.67
Construction Started
Sanction on : 4 years 1 month ago
25 May 2021
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
50 %
Tentative Completion date on : 2 months 3 weeks ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति में है। -- as on 05-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand