Work Profile Report [20W41]

स्यूतीगाड़ राममंदिर मोटर मार्ग से ब्याती - थामा मोटर मार्ग
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0 सं0 764/111 (2)/ 08 -80 (प्रा0आ0) /07 दि0 24/3/08

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

110.25

Resanction Cost :

110.25

Tentative Cost :

0.48

Saving

109.77

Exp. Upto Last Fy :

0.48

For CFY 2024-2025

Remaining :

109.77

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

0.48

Unstarted Work

Sanction on : 16 years 10 months ago

24 Mar 2008

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

0 %

Tentative Completion date on : 1 year 1 month from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000

Remark

view all

दि0 30.07.2024 को सचिव महोदय द्वारा वन भूमि की आनलाईन बैठक में प्राप्त निर्देशों के क्रम में निरस्तीकरण प्रस्ताव मुख्य अभियन्ता लो0 नि0 वि0 अल्मोड़ा के पत्रांक 6212/06 याता0(नियो0-5)-अ0/2024 दि020.11.2024 से प्रमुख अभियन्ता विभागाध्यक्ष को प्रेषित है। -- as on 30-Dec-2024

Rating : 1

Forest Case Pending At : 02: Division

Hindrance / Bottleneck : To Cancel

Assets :

Work not linked with IM

Bridges on The Basis of AI: