Work Profile Report [20W421]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 2565/ III(2)/18-45 (एम.एल.ए.)/2017 दि0 12 जून 2018
TS Amount (lakhs) : 3.8 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.45
Resanction Cost :
6.45
Tentative Cost :
3.18
Saving
3.27
Exp. Upto Last Fy :
3.18
For CFY 2025-2026
Remaining :
3.27
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.18
Phase1 DPR Submitted
Sanction on : 7 years 1 week ago
12 Jun 2018
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 day ago
24 May 2025
Actual Completion Date : 1 year 2 months ago
29 Mar 2024
Physical Linear Components
Remark
डी0पी0आर गठित कर मु0 अभि0 लो0 नि0 वि0 अल्मोड़ा के पत्रांक 1803/भवन-अ0/2021 दि0 24.05.2021 से शासन को प्रेषित । -- as on 20-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: