Work Profile Report [20W448]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0 सं0 5633/।।। (2)/21-45 (एम0एल0ए0)/2017 दि0 17 नवम्बर 2021
TS Amount (lakhs) : 339.12 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
339.12
Resanction Cost :
355.45
Tentative Cost :
355.45
Exp. Upto Last Fy :
344.63
For CFY 2024-2025
Remaining :
10.82
Demand :
2.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
344.63
In Maintenance After Completion
Sanction on : 3 years 6 days ago
17 Nov 2021
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 2 months ago
30 Aug 2023
Actual Completion Date : 1 year 4 months ago
30 Jun 2023
Physical Linear Components
Remark
निर्माण कार्य पूर्ण । तीन वर्षीय अनुरक्षण का कार्य किया जा रहा है। -- as on 21-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand