Work Profile Report [20W533]

केन्द्र पोषित योजनान्तर्गत जनपद पिथौरागढ़ के गंगोलीहाट में सिविल जज न्याायालय भवन की निर्माण कार्य ।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : E file N0- 55281/XXXVI(2)/23/8-budget/2023 dt- 06.06.2023

TS Amount (lakhs) : 443.88 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

477.50

Resanction Cost :

477.50

Tentative Cost :

477.50

Exp. Upto Last Fy :

0.00

For CFY 2024-2025

Remaining :

477.50

Demand :

215.00

Allotment :

125.00

Exp in CFY :

44.02

Total Up to Date Exp :

44.02

Construction Started

Sanction on : 1 year 6 months ago

29 May 2023

Physical Progress:

At start of FY 2024-2025 :

0 %

Up to Date :

15 %

Tentative Completion date on : 10 months 2 weeks from now

14 Nov 2025

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Buildings
1
1
0
1
0
0

Remark

view all

दि0 15.03.2024 द्वारा अनुबंध गठित। भवन का स्थल विकास का कार्य लगभग 80ः तक पूर्ण हो चुका है। अवशेष स्थल विकास हेतु ब्लास्टिंग की आवश्यकता हो रही है। जिसके लिए अनुमति लेने की कार्यवाही की जा रही है। स्थल पर भवन की नीव का कार्य प्रारम्भ् कर दिया लिया गया है। वर्तमान में 18 कालम की फुटिंग का कार्य गतिमान है तथा 1 सप्ताह के अन्तर्गत यह कार्य प्लिन्थ लेबल तक पहुच जायेगा। स्थल पर 5 देवदार के पड़ों का पातन होना है जिससे अवशेष फुटिंग का कार्य प्रारम्भ नही किया जा सका है। प्रभागीय वनाधिकारी तथा सी0डी0ओ0 कार्यालय को जानकारी प्रदान कर दी गयी है। वन निगम से भी लगातार सम्पर्क किया जा रहा है। -- as on 10-Dec-2024

Rating : 34

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: