Work Profile Report [20W536]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : शासनादेश संख्या 2937/।।।(2)/ 23-01(प्रा0आ0)/2019 दि0 11.08.2023
TS Amount (lakhs) : 416.79 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
416.79
Resanction Cost :
416.79
Tentative Cost :
416.79
Exp. Upto Last Fy :
218.04
For CFY 2024-2025
Remaining :
198.75
Demand :
198.75
Allotment :
160.00
Exp in CFY :
50.07
Total Up to Date Exp :
268.12
Construction Started
Sanction on : 1 year 5 days ago
11 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
90 %
Tentative Completion date on : 2 weeks 23 hours from now
31 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रैश बैरियर लगाये जाने का कार्य पूर्ण । शेष कार्य प्रगति पर है। -- as on 14-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand