Work Profile Report [22W1064]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Administrative Approval Detail : श्शासनादेश संख्या 2499/।।। (2)/17-56 (एम0एल0ए0)/2017,दिनाॅक 15.11.2017
TS Amount (lakhs) : 17 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
17.00
Resanction Cost :
17.00
Tentative Cost :
17.00
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
16.90
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Unstarted Work
Sanction on : 6 years 9 months ago
15 Nov 2017
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 3 years 4 months ago
31 Mar 2021
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
fववाद सुलझा fदया गया है। fनfवदा आमंfत्रत होनी है। -- as on 31-Jul-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI: