Work Profile Report [22W1180]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शासनादेश संख्या 4582/।।। (2)/19-60 (एम0एल0ए0)/2017, दिनाॅक 24.12.2019 द्वारा स्वीकृत
TS Amount (lakhs) : 74.12 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
74.12
Resanction Cost :
74.12
Tentative Cost :
74.12
Exp. Upto Last Fy :
74.05
For CFY 2025-2026
Remaining :
0.07
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
74.05
Work completed
Sanction on : 5 years 7 months ago
24 Dec 2019
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 4 years 4 months ago
31 Mar 2021
Actual Completion Date : 4 years 5 months ago
01 Mar 2021
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand