Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.2 | 8.2 | 8.200 | 0 | 0.000 | 0.000 |
22W1191 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश संख्या 643/।।। (2)/20-60 (एम0एल0ए0)/2017 टी0सी0, दिनाॅक 12.02.2020 द्वारा स्वीकृत
TS Amount (lakhs) : 189.44 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
189.44
Resanction Cost :
189.44
Tentative Cost :
189.44
Exp. Upto Last Fy : 102.21
For CFY 2024-2025
Remaining : 87.23
Demand : 2.38
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 102.21
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 5 months ago
12 Feb 2020
Tentative Completion date:
3 years 3 months ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्णं। दायित्व शेष। -- as on 02-Jun-2022
Physical Peramenters