Work Profile Report [22W1325]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : प्रमुख सचिव, उत्तराखण्ड शासन का ई-फाईल संख्या 33064 लोक निर्माण अनुभाग-2, देहरादून, दिनाॅक 09.11.2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
81.42
Resanction Cost :
81.42
Tentative Cost :
81.42
Exp. Upto Last Fy :
77.45
For CFY 2024-2025
Remaining :
3.97
Demand :
7.94
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
77.45
Construction Started
Sanction on : 2 years 1 month ago
09 Nov 2022
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
80 %
Tentative Completion date on : 3 months 4 days from now
30 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 10-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: