Work Profile Report [22W1369]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 25/54 budget road safety (23-24)
TS Amount (lakhs) : 96.82 Lacs
Budget Financial Head : सड़क सुरक्षा कार्य ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
96.82
Resanction Cost :
96.82
Tentative Cost :
96.82
Exp. Upto Last Fy :
87.60
For CFY 2024-2025
Remaining :
9.22
Demand :
9.22
Allotment :
87.60
Exp in CFY :
0.93
Total Up to Date Exp :
88.53
Construction Started
Sanction on : 1 year 5 months ago
20 Jun 2023
Physical Progress:
At start of FY 2024-2025 :
80 %
Up to Date :
100 %
Tentative Completion date on : 10 months 1 week ago
13 Jan 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष -- as on 13-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand