Work Profile Report [22W1377]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-PART (1) 917/2023 E-File No. 53698, dt. 19-07-2023
TS Amount (lakhs) : 47.15 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.15
Resanction Cost :
47.15
Tentative Cost :
47.15
Exp. Upto Last Fy :
20.31
For CFY 2024-2025
Remaining :
26.84
Demand :
26.00
Allotment :
20.00
Exp in CFY :
16.49
Total Up to Date Exp :
36.80
Construction Started
Sanction on : 1 year 4 months ago
19 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
95 %
Tentative Completion date on : 3 months 3 weeks ago
30 Jul 2024
Actual Completion Date : 2 months 1 week ago
10 Sep 2024
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 20-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: