Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.3 | 2.3 | 0.000 | 2.3 | 0.500 | 0.000 |
22W1400 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-5607/2023 E-File No. 53170, dt. 11.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
29.15
Resanction Cost :
29.15
Tentative Cost :
29.15
Exp. Upto Last Fy : 11.16
For CFY 2024-2025
Remaining : 17.99
Demand : 10.00
Allotment : 17.22
Exp in CFY : 17.22
Total Up to Date Exp : 28.38
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
11 months 6 days ago
11 Aug 2023
Tentative Completion date:
1 month 1 week from now
27 Aug 2024
Actual Completion Date:
2 months 2 weeks ago
28 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-Jul-2024
Physical Peramenters