Work Profile Report [22W1406]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-5607/2023 E-File No. 53170, dt. 11.08.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
26.26
Resanction Cost :
26.26
Tentative Cost :
26.26
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
26.16
Demand :
25.00
Allotment :
25.58
Exp in CFY :
26.07
Total Up to Date Exp :
26.17
Construction Started
Sanction on : 1 year 3 months ago
11 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 1 month 6 days from now
30 Dec 2024
Actual Completion Date : 6 months 4 weeks ago
25 Apr 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 02-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand