Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
22W1421 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/2/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 08-09-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
60.75
Resanction Cost :
60.75
Tentative Cost :
60.75
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 60.65
Demand : 30.00
Allotment : 12.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
2 months 2 days from now
20 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दिनांक 04.06.2024 को LOA जारी हो चुका है | दिनांक 08.07.2024 तक अनुबंध गठित कर कार्य आरंभ कर लिया जाएगा | -- as on 01-Jul-2024
Physical Peramenters