Work Profile Report [22W1421]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/2/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 08-09-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
60.75
Resanction Cost :
60.75
Tentative Cost :
60.75
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
60.65
Demand :
36.50
Allotment :
30.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.10
Construction Started
Sanction on : 1 year 3 months ago
08 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
20 %
Tentative Completion date on : 3 months 5 days ago
20 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 03-Sep-2024
Assets :
Work not linked with IM