Work Profile Report [22W1422]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/2/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 08-09-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.35
Resanction Cost :
56.35
Tentative Cost :
56.35
Exp. Upto Last Fy :
12.05
For CFY 2024-2025
Remaining :
44.30
Demand :
34.00
Allotment :
30.00
Exp in CFY :
22.30
Total Up to Date Exp :
34.36
Construction Started
Sanction on : 1 year 3 months ago
08 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
85 %
Tentative Completion date on : 2 months 3 weeks ago
30 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 20-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: