Work Profile Report [22W1433]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/46/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 12-10-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
48.49
Resanction Cost :
48.49
Tentative Cost :
48.49
Exp. Upto Last Fy :
8.73
For CFY 2024-2025
Remaining :
39.76
Demand :
28.51
Allotment :
8.00
Exp in CFY :
27.58
Total Up to Date Exp :
36.31
Construction Started
Sanction on : 1 year 1 month ago
12 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
50 %
Tentative Completion date on : 1 month 1 week ago
11 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर | -- as on 11-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand