Work Profile Report [22W1453]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 821/बजट आवंटन/जि०यो० /स्वी०/लो०नि०वि०/24-32/2023-24
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
24.09
Resanction Cost :
24.09
Tentative Cost :
24.09
Exp. Upto Last Fy :
1.73
For CFY 2024-2025
Remaining :
22.36
Demand :
8.94
Allotment :
8.94
Exp in CFY :
8.80
Total Up to Date Exp :
10.52
Construction Started
Sanction on : 1 year 1 month ago
16 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 30-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand