Work Profile Report [22W1504]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 889/budget allotment/ZY/2024-25
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
202.88
Resanction Cost :
92.54
Tentative Cost :
92.54
Exp. Upto Last Fy :
43.01
For CFY 2025-2026
Remaining :
49.53
Demand :
49.53
Allotment :
3.50
Exp in CFY :
14.41
Total Up to Date Exp :
57.42
Construction Started
Sanction on : 8 months 1 week ago
26 Nov 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
85 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति। -- as on 30-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand