Work Profile Report [22W1507]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E file No 48808/60
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
46.10
Resanction Cost :
46.10
Tentative Cost :
46.10
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
46.00
Demand :
30.00
Allotment :
38.85
Exp in CFY :
38.85
Total Up to Date Exp :
38.95
Construction Started
Sanction on : 7 months 1 day ago
17 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
80 %
Tentative Completion date on : 2 months 3 weeks from now
15 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0 , जी2, जी3 का कार्य पूर्ण, 300 मी0 में पी0सी0 का कार्य पूर्ण, अवशेष कार्य प्रगति पर। -- as on 10-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: