Administrative Approval Detail : E-file No. 70174/60, dt. 23.12.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
61.88
Resanction Cost :
61.88
Tentative Cost :
61.88
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
61.78
Demand :
50.00
Allotment :
25.08
Exp in CFY :
25.08
Total Up to Date Exp :
25.18
Construction Started
Sanction on : 6 months 4 days ago
23 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
50 %
Tentative Completion date on : 3 months 2 weeks from now
16 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति। -- as on 28-Apr-2025