Administrative Approval Detail : E-file No. 70174/60, dt. 23.12.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
61.88
Resanction Cost :
61.88
Tentative Cost :
61.88
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
61.78
Demand :
61.78
Allotment :
25.20
Exp in CFY :
25.20
Total Up to Date Exp :
25.30
Construction Started
Sanction on : 11 months 3 weeks ago
23 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
60 %
Tentative Completion date on : 3 months 2 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी3 तक का कार्य पूर्ण, 0.5 में पी0सी0 का कार्य पूर्ण, शेष प्रगति पर। -- as on 06-Nov-2025