Work Profile Report [22W1613]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E-file No. 83534/56, dt. 14.05.2025
TS Amount (lakhs) : 18.65 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
18.65
Resanction Cost :
18.65
Tentative Cost :
18.65
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
18.65
Demand :
18.00
Allotment :
0.32
Exp in CFY :
0.16
Total Up to Date Exp :
0.16
Construction Started
Sanction on : 8 months 1 week ago
14 May 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
25 %
Tentative Completion date on : 1 month 14 hours from now
24 Feb 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 11-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: