Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
23W1008 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं01458/।।।(2)/20- 67(एम.एल.ए.)/2017 टी.सी. दिनांक 10.08.2020 (प्रथम चरण)
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
70.45
Resanction Cost :
70.45
Tentative Cost :
70.45
Exp. Upto Last Fy : 16.42
For CFY 2024-2025
Remaining : 54.03
Demand : 10.00
Allotment : 0.00
Exp in CFY : 7.89
Total Up to Date Exp : 24.31
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 11 months ago
10 Aug 2020
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 14-Nov-2023
Physical Peramenters