Work Profile Report [23W1166]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/118165/2023 e-file no.- 51571
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2.64
Resanction Cost :
2.64
Tentative Cost :
2.64
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
2.64
Demand :
2.64
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Work completed
Sanction on : 1 year 6 months ago
01 May 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 weeks ago
31 Oct 2023
Actual Completion Date : 7 months 3 weeks ago
31 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 18-Nov-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand