Work Profile Report [23W1168]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/119401/2023 e-file no.- 49076
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
56.94
Resanction Cost :
56.94
Tentative Cost :
48.06
Saving
8.88
Exp. Upto Last Fy :
15.19
For CFY 2024-2025
Remaining :
41.75
Demand :
40.00
Allotment :
34.84
Exp in CFY :
34.84
Total Up to Date Exp :
50.03
Work completed
Sanction on : 1 year 7 months ago
04 May 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 6 months 2 weeks ago
11 Jun 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 8.88 has been recorded as expected cost of work reduced from 56.94 to 48.06 . -- as on 17-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: