Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.55 | 0.55 | 0.000 | 0.55 | 0.550 | 0.000 |
23W1170 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/119401/2023 e-file no.- 49076
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
14.05
Resanction Cost :
14.05
Tentative Cost :
14.05
Exp. Upto Last Fy : 6.56
For CFY 2024-2025
Remaining : 7.49
Demand : 7.00
Allotment : 0.00
Exp in CFY : 5.99
Total Up to Date Exp : 12.54
Work completed
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
04 May 2023
Tentative Completion date:
3 months 1 week ago
04 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 26-Jun-2024
Physical Peramenters