Work Profile Report [23W1175]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : G.O. no.- I/121103/2023 e-file no.- 52003
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
67.98
Resanction Cost :
67.98
Tentative Cost :
67.98
Exp. Upto Last Fy :
17.18
For CFY 2024-2025
Remaining :
50.80
Demand :
45.00
Allotment :
24.33
Exp in CFY :
24.33
Total Up to Date Exp :
41.51
Work completed
Sanction on : 1 year 3 months ago
11 May 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 1 month 1 week from now
30 Sep 2024
Actual Completion Date : 1 month 2 weeks ago
30 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 14-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: