Work Profile Report [23W1180]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : G.O. no.- I/121103/2023 e-file no.- 52003
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.96
Resanction Cost :
47.96
Tentative Cost :
47.96
Exp. Upto Last Fy :
20.65
For CFY 2024-2025
Remaining :
27.31
Demand :
26.00
Allotment :
27.15
Exp in CFY :
27.31
Total Up to Date Exp :
47.96
Construction Started
Sanction on : 1 year 3 months ago
11 May 2023
Physical Progress:
At start of FY 2024-2025 :
60 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 weeks ago
21 May 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 01-Jul-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand