Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.6 | 2.6 | 1.600 | 1 | 1.000 | 0.000 |
23W1185 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/121103/2023 e-file no.- 52003
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
89.25
Resanction Cost :
89.25
Tentative Cost :
89.25
Exp. Upto Last Fy : 76.84
For CFY 2024-2025
Remaining : 12.41
Demand : 10.00
Allotment : 0.00
Exp in CFY : 16.78
Total Up to Date Exp : 93.62
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
11 May 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 01-Jul-2024
Physical Peramenters