Work Profile Report [23W1186]

Gadarpur Dineshpur Matkota Haldwani state highway-5 at Km 15 (Chainage 14.900)
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks

    Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : Go no. 881/III(3)/2023-12 (एन०एच०) 2018 dated 14-07-2023

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : CRIF ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

5538.80

Resanction Cost :

5538.80

Tentative Cost :

5538.80

Exp. Upto Last Fy :

65.43

For CFY 2025-2026

Remaining :

5,473.37

Demand :

0.00

Allotment :

11.24

Exp in CFY :

11.24

Total Up to Date Exp :

76.66

Unstarted Work

Sanction on : 1 year 11 months ago

14 Jul 2023

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

0 %

Tentative Completion date on : 8 months 3 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Bridge
1 (120m)
1 (120m)
1 (120m)
-

Remark

view all

प्रथम चरण का कार्य प्रगति पर। -- as on 24-Oct-2024

Rating : 2

No Forest Case in The Work

Hindrance / Bottleneck : Other Reason

Assets :

Work not linked with IM

Bridges on The Basis of AI: