Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
23W1189 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/133749/2023 e-file no.- 53091
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
64.03
Resanction Cost :
64.03
Tentative Cost :
64.03
Exp. Upto Last Fy : 16.74
For CFY 2024-2025
Remaining : 47.29
Demand : 46.00
Allotment : 0.00
Exp in CFY : 26.00
Total Up to Date Exp : 42.73
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
1 year 2 weeks ago
30 Jun 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 01-Jul-2024