Work Profile Report [23W1194]
Tenders
Project Activities
alerts
Documents
Administrative Approval Detail : G.O. no.- I/152057/2023 e-file no.- 43713
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
45.87
Resanction Cost :
45.87
Tentative Cost :
45.87
Exp. Upto Last Fy :
25.17
For CFY 2024-2025
Remaining :
20.70
Demand :
20.00
Allotment :
18.79
Exp in CFY :
18.79
Total Up to Date Exp :
43.96
Work completed
Sanction on : 1 year 4 months ago
31 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
30 Oct 2024
Actual Completion Date : 6 months 3 weeks ago
31 May 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 20-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: