Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.525 | 0.525 | 0.000 | 0.525 | 0.520 | 0.000 |
23W1195 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/152057/2023 e-file no.- 43713
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
14.31
Resanction Cost :
14.31
Tentative Cost :
14.31
Exp. Upto Last Fy : 8.33
For CFY 2024-2025
Remaining : 5.98
Demand : 4.00
Allotment : 0.00
Exp in CFY : 4.67
Total Up to Date Exp : 12.99
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
2 months 1 week from now
27 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 01-Dec-2023
Physical Peramenters