Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.35 | 1.35 | 0.000 | 1.35 | 1.000 | 0.000 |
23W1208 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/167411/2023, e- File no.- 43713, Date- 07.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
96.16
Resanction Cost :
96.16
Tentative Cost :
96.16
Exp. Upto Last Fy : 61.45
For CFY 2024-2025
Remaining : 34.71
Demand : 32.00
Allotment : 0.00
Exp in CFY : 10.44
Total Up to Date Exp : 71.90
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
8 months 1 week ago
07 Nov 2023
Tentative Completion date:
3 months 2 days ago
15 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 20-Jun-2024
Physical Peramenters