Work Profile Report [23W1209]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/175556/2023 e-file no.- 51571
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
27.46
Resanction Cost :
27.46
Tentative Cost :
27.46
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
27.46
Demand :
25.00
Allotment :
16.84
Exp in CFY :
25.33
Total Up to Date Exp :
25.33
Construction Started
Sanction on : 11 months 5 days ago
18 Dec 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
20 %
Tentative Completion date on : 2 months 2 weeks ago
04 Sep 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 02-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand